PMI CAPM · Certified Associate in Project Management · free practice

CAPM practice exam: 10 free questions, every option explained

Ten questions from the course across all four domains of PMI's CAPM outline: risks and constraints, projects versus operations, ethics, critical path and schedule variance, Kanban and sprint planning, traceability, acceptance criteria and product roles. Answer, then read why each option is right or wrong.

  • 150 questions
  • 3 hours
  • 36 / 17 / 20 / 27 weighting
  • No published passing score
CAPM practice exams course cover

The exam, from PMI

150 questions, 3 hours135 scored and 15 unscored pretest questions, mixed in at random. A 10-minute break comes after question 75.
No published passing scorePMI sets the passing score by psychometric analysis and reports pass or fail with feedback by domain.
Education, not experienceA high school diploma, GED or global equivalent plus 23 hours of project management education; the outline lists no experience requirement.
More than multiple choiceDrag and drop, hot spots, and short animations or comic strips, each followed by one question.

From PMI's CAPM Examination Content Outline (the 2023 exam update) and the PMI Certification Handbook (revised June 2026). More in the CAPM exam format guide.

10 free CAPM practice questions

Taken from the course, at least two from every domain, including two calculations and two multiple-response items. Click an option to answer; the explanation under every option appears as soon as you do.

  1. Project Management Fundamentals and Core ConceptsQuestion 1 of 10 · choose two

    While planning a public library system's rollout of RFID self-checkout stations, the project manager reviews notes from a hybrid planning workshop. Which TWO notes should be recorded in the risk register? (Choose TWO.)

    1. The vendor's tags might not read reliably on books with metal-reinforced spines.
    2. The plan takes as given that every branch will keep its current opening hours during rollout.
    3. The library board has capped total project spending at $400,000 for this fiscal year.
    4. If union contract talks run past March, staff training on the new stations could be delayed.
    5. Wi-Fi at two branches failed yesterday and halted all checkouts for four hours.
    Show the answer and why

    Answer: A and D

    • A. Correct. This is an uncertain future event that, if it occurs, would affect the deliverable, which is exactly what a risk is.
    • B. This is an assumption, something treated as true for planning. It belongs in the assumption log and should be validated; a risk is raised only if analysis shows it may prove false.
    • C. A fixed budget cap limits the team's options. It is a constraint and is documented with the other constraints, not in the risk register.
    • D. Correct. The cause, the uncertain event, and the effect on training are all stated, which makes this a well-formed risk.
    • E. This has already happened and is affecting service now, so it is an issue to log and resolve, not a risk.

    Why it matters: A risk is an uncertain event or condition that, if it occurs, has an effect on project objectives. Issues have already occurred, constraints are limits on options such as a budget cap, and assumptions are factors treated as true without proof. Exam tip: Might happen: risk. Has happened: issue. Must work within: constraint. Believed true: assumption.

  2. Project Management Fundamentals and Core ConceptsQuestion 2 of 10

    A utility supervisor says the annual tree-trimming cycle along power lines should be run as a project because it has its own budget and schedule each year. Why is this view incorrect?

    1. Work performed by field crews is always classified as operations
    2. The work repeats each year with the same result, so it is operations
    3. Tree trimming has no sponsor, so it cannot be treated as a project
    4. Projects cannot be funded through budgets that are approved every year
    Show the answer and why

    Answer: B

    • A. Field crews can work on projects, such as building a new line; the nature of the work, not who does it, determines the classification.
    • B. Correct. Repetitive, ongoing work that produces the same outcome each cycle is operations, even if it is planned and budgeted.
    • C. Having or lacking a sponsor is not what separates projects from operations; the repetitive nature of the work is.
    • D. Projects can be funded through annual budgets; budgeting cycles do not determine whether work is a project.

    Why it matters: Projects are temporary and produce unique results, while operations are ongoing and repetitive. Planning and budgeting recurring work does not make it a project. Exam tip: Budgets and schedules do not make work a project; uniqueness and a defined end do.

  3. Project Management Fundamentals and Core ConceptsQuestion 3 of 10

    A sponsor asks a project manager to lead a GMP computer system validation project at a biotech plant, assuming she has done validation work before. She has managed software projects but has never led a validation effort. What should she do?

    1. Accept without comment and learn validation on the job, so that she does not disappoint the sponsor
    2. Accept and rely entirely on the vendor's validation package, so that her inexperience does not matter at all
    3. Decline the assignment, because the Code of Ethics forbids accepting any work that is unfamiliar
    4. Tell the sponsor about her experience gap and propose ways to cover it, such as adding a validation lead
    Show the answer and why

    Answer: D

    • A. Hiding the gap leaves the sponsor with a false picture of her qualifications, which conflicts with honesty and responsibility.
    • B. Relying blindly on a vendor package does not close her knowledge gap and may leave compliance risks unnoticed.
    • C. The Code allows stretch assignments, as long as key stakeholders receive timely and complete information about the gaps.
    • D. Correct. Being honest about the gap lets the sponsor make an informed decision, and proposing support shows responsibility for the outcome.

    Why it matters: The PMI Code of Ethics asks practitioners to accept only assignments consistent with their background, experience, and qualifications, and, for stretch assignments, to give key stakeholders timely and complete information about any gaps. Honesty about qualifications lets the sponsor decide with full information. Exam tip: Stretch assignments are fine if you are honest about the gaps and propose how to cover them.

  4. Predictive, Plan-Based MethodologiesQuestion 4 of 10

    A telecom switch installation has three paths: A (3 days) to B (5 days) to E (4 days); A to C (6 days) to E; and A to D (2 days) to E. What are the critical path and the total float of activity B?

    1. A-C-E, and activity B has 4 days of total float
    2. A-D-E, and activity B has 1 day of total float
    3. A-B-E, and activity B has 0 days of total float
    4. A-C-E, and activity B has 1 day of total float
    Show the answer and why

    Answer: D

    • A. Four days is the float of activity D (13 minus 9); the path through B is only 1 day shorter than the critical path.
    • B. A-D-E is the shortest path at 9 days; the critical path is the longest path through the network.
    • C. A-B-E totals 12 days, which is shorter than A-C-E at 13 days, so it is not critical and B has float.
    • D. Correct. A-C-E is 13 days, the longest path, and A-B-E is 12 days, so B can slip 1 day without delaying the project.

    Why it matters: Path durations: A-B-E = 3 + 5 + 4 = 12, A-C-E = 3 + 6 + 4 = 13, and A-D-E = 3 + 2 + 4 = 9, so A-C-E is critical at 13 days. For B, ES = 3 and LS = 9 minus 5 = 4 (E must start by day 9), so total float = LS minus ES = 4 minus 3 = 1 day. Exam tip: The longest path is critical. Total float equals LS minus ES.

  5. Predictive, Plan-Based MethodologiesQuestion 5 of 10

    A hybrid project is delivering a new residence hall booking system for a university. For the predictive vendor-integration work, the week 10 status report shows planned value of $80,000, earned value of $68,000, and actual cost of $70,000. What is the schedule variance, and what does it indicate?

    1. −$12,000, so the integration work is behind schedule
    2. +$12,000, so the integration work is ahead of schedule
    3. −$12,000, so the integration work is over budget
    4. −$2,000, so the integration work is behind schedule
    Show the answer and why

    Answer: A

    • A. Correct. SV = EV − PV = $68,000 − $80,000 = −$12,000, which means less work has been done than planned.
    • B. The sign is reversed. Subtracting EV from PV gives +$12,000, but the formula is EV minus PV, so the result is negative.
    • C. The amount is right, but schedule variance describes schedule performance. Being over or under budget is measured with cost variance.
    • D. −$2,000 is the cost variance (EV − AC), not the schedule variance, and it describes cost rather than schedule.

    Why it matters: SV = EV − PV = $68,000 − $80,000 = −$12,000. A negative schedule variance means less work has been completed than planned at this point. Cost performance is measured separately with CV = EV − AC, which here is −$2,000. Exam tip: SV compares EV to PV (schedule). CV compares EV to AC (cost). Negative means behind or over.

  6. Agile Frameworks/MethodologiesQuestion 6 of 10

    A travel agency's itinerary team uses a Kanban board. The Review column has a WIP limit of 3 and already holds three items when a writer finishes a new draft. What should the writer do?

    1. Start another draft so that she stays fully busy
    2. Ask the manager to raise the Review WIP limit today
    3. Help clear an item in Review before pulling more work
    4. Move the draft into Review and note the exception
    Show the answer and why

    Answer: C

    • A. Starting more work increases work in progress and lengthens cycle time while the bottleneck remains.
    • B. Teams can adjust WIP limits over time, but raising one just to fit more work hides the bottleneck.
    • C. Correct. Kanban favors finishing work over starting new work, so she helps relieve the bottleneck in Review.
    • D. Exceeding the WIP limit defeats its purpose of exposing bottlenecks and keeping work flowing.

    Why it matters: WIP limits make bottlenecks visible and enforce a pull system: work moves only when the next column has capacity. When a column is full, team members swarm to finish the work there, following the idea of stop starting, start finishing. Exam tip: Column at its WIP limit? Stop starting, start finishing.

  7. Agile Frameworks/MethodologiesQuestion 7 of 10

    A Scrum team building a data platform for a clinical laboratory works in two-week sprints. The top backlog item, 'Integrate all lab instruments with the platform', is far too large to finish in one sprint. What is the BEST way to plan for it?

    1. Extend the upcoming sprint to five weeks so that the whole item can be completed within a single sprint
    2. Keep the two-week timebox and split the item into valuable slices, such as one instrument type each
    3. Split the item by technical layer, with database work in one sprint and user interface work in a later one
    4. Start the whole item now and carry whatever is unfinished into the next sprint as a planned continuation
    Show the answer and why

    Answer: B

    • A. Sprints are fixed-length timeboxes. Stretching one sprint to fit a large item breaks the regular inspect-and-adapt rhythm.
    • B. Correct. Timeboxes stay fixed, and large items are split into thin, end-to-end slices that can each be finished and reviewed within a sprint.
    • C. Splitting by layer creates pieces that deliver no usable value on their own. Vertical slices through all layers are preferred.
    • D. Planning to carry unfinished work forward means no usable increment for that item this sprint and weakens forecasting.

    Why it matters: Iterations are timeboxed, so work is shaped to fit the timebox rather than the reverse. Large items are split into smaller slices that each deliver value and can meet the Definition of Done within one iteration. Exam tip: Fit the work to the timebox, not the timebox to the work. Slice vertically so each piece delivers value.

  8. Business Analysis FrameworksQuestion 8 of 10 · choose two

    A business analyst maintains a requirements traceability matrix for a new production-planning system at a truck plant. Which TWO are valid uses of the matrix? (Choose TWO.)

    1. Tracking the team's velocity from one sprint to the next
    2. Recording each stakeholder's preferred communication channel
    3. Assigning daily tasks to the developers and tracking the hours they work each week
    4. Confirming that every requirement links to an approved business objective
    5. Confirming that every requirement is covered by at least one test case
    Show the answer and why

    Answer: D and E

    • A. Velocity is tracked in agile charts and reports, not in requirement traceability.
    • B. Communication preferences belong in the stakeholder register or the communications management plan.
    • C. Task assignments and hours are tracked in schedules, task boards, or timesheets, not in a traceability matrix.
    • D. Correct. Tracing requirements back to objectives shows that each one adds business value and helps prevent scope creep.
    • E. Correct. Tracing forward to test cases shows whether each requirement will be verified, which reveals coverage gaps.

    Why it matters: The traceability matrix links requirements backward to their business objectives and sources and forward to design and tests. Backward tracing confirms value and helps control scope; forward tracing confirms that every requirement is built and tested. Exam tip: Trace back to confirm value and control scope; trace forward to confirm build and test coverage.

  9. Business Analysis FrameworksQuestion 9 of 10

    The product owner for a university's course registration system wrote this user story: 'As a student on a waitlist, I want to be notified when a seat opens so that I can enroll before someone else.' Which acceptance criterion is written MOST effectively?

    1. A scheduled job checks the enrollment table every five minutes and then sends the alert
    2. Waitlisted students are satisfied with the way they find out about seats that open up in a section
    3. The system should notify waitlisted students quickly and reliably whenever a seat in their section opens
    4. Given I am first on a full section's waitlist, when a student drops, then I get an email within 15 minutes
    Show the answer and why

    Answer: D

    • A. This describes how to build the feature, not the behavior the student should experience. Acceptance criteria focus on outcomes.
    • B. Satisfaction is not directly testable at the story level. A criterion needs a clear pass or fail condition.
    • C. Words like 'quickly' and 'reliably' cannot be tested objectively, so the team and product owner could disagree about whether it passes.
    • D. Correct. The Given/When/Then format states the context, the trigger, and an observable, measurable result.

    Why it matters: Good acceptance criteria are specific, testable, and written from the user's perspective. The Given/When/Then format states the starting context, the triggering event, and the observable result, here including a measurable time limit. Vague wording, implementation details, and satisfaction statements cannot be objectively tested. Exam tip: Given the context, When the event occurs, Then an observable, measurable result follows.

  10. Business Analysis FrameworksQuestion 10 of 10

    At a telecom company, a product manager sets long-term strategy for the prepaid mobile line, while a product owner works daily with a Scrum team on the companion app. Which responsibility belongs MOST to the product owner?

    1. Ordering the product backlog and clarifying items for the Developers
    2. Approving the overall funding for the companion app initiative
    3. Setting market strategy and pricing for the entire prepaid line
    4. Facilitating all Scrum events and removing impediments that block the team
    Show the answer and why

    Answer: A

    • A. Correct. The product owner maximizes value by ordering the product backlog and making sure the Developers understand its items.
    • B. Approving overall funding is typically a sponsor responsibility.
    • C. Long-term market strategy and pricing for the whole product line fit the product manager's role in this scenario.
    • D. Facilitating events and removing impediments are Scrum Master responsibilities.

    Why it matters: A product manager typically owns the product's long-term strategy across its life cycle. In Scrum, the product owner is accountable for maximizing the value delivered by the team, mainly by managing and ordering the product backlog. Exam tip: Product owner: owns and orders the backlog. Product manager: owns long-term product strategy.

The four domains

DomainWeightQuestions per 150-question course examTasks in the outline
1. Project Management Fundamentals and Core Concepts36%545
2. Predictive, Plan-Based Methodologies17%263
3. Agile Frameworks/Methodologies20%305
4. Business Analysis Frameworks27%406

Weights and tasks from the CAPM Examination Content Outline. PMI says every exam includes all tasks of each domain, and that predictive, adaptive and business analysis approaches are found throughout the four domains rather than in one of them. Agile and business analysis together are 47% of the exam.

What the CAPM really tests

Not the old ITTO drill. Before the 2023 update, PMI says, the CAPM tested only the concepts in the PMBOK Guide Sixth Edition. Today's outline has four domains, and every question must be supported by at least two of PMI's references, among them the PMBOK Guide Seventh Edition, the Agile Practice Guide and The PMI Guide to Business Analysis.

Core vocabulary in scenarios. Project, program or portfolio; project or operations; issue, risk, assumption or constraint; project manager, sponsor or team; leadership or management.

Predictive and adaptive. Critical path, schedule and cost variance, WBS and work packages, then iterations, backlogs and the components of Scrum, Extreme Programming, SAFe and Kanban.

Business analysis. Stakeholder roles such as product owner and product manager, requirements gathering, the requirements traceability matrix, product roadmaps and acceptance criteria.

What's inside the course

1

Six full practice exams

Six tests of 150 questions, 900 original questions, each timed at 3 hours and split 54/26/30/40 across the four domains.

2

Every option explained

Why the right answer fits and why each wrong option fails in that scenario, plus an exam tip on every question.

3

The math, step by step

Critical path and float, schedule and cost variance, CPI and SPI, plus 14 multiple-response items per exam, marked Choose TWO.

Six full exams, 900 questions, all options explained

150 questions and 3 hours per test, the real exam's length and time, with a score breakdown by domain.

See the CAPM course →

CAPM practice exam FAQ

How many questions are on the CAPM exam?

150 questions in 3 hours. According to PMI's Examination Content Outline, 135 are scored and 15 are unscored pretest questions placed at random. There is a 10-minute break after question 75.

What is the CAPM passing score?

PMI does not publish one. Its certification handbook says the passing score for all PMI exams is determined by sound psychometric analysis, and your score report gives pass or fail plus diagnostic information by domain. Our 75% target on unseen practice exams is ours, not PMI's.

What are the CAPM domains and weights?

Project Management Fundamentals and Core Concepts 36%, Predictive, Plan-Based Methodologies 17%, Agile Frameworks/Methodologies 20%, and Business Analysis Frameworks 27%. PMI says predictive, adaptive and business analysis approaches appear throughout all four domains.

What do I need to be eligible for the CAPM?

A secondary degree (a high school diploma, GED or global equivalent) and 23 hours of project management education, completed by the time of your exam. The outline does not ask for project experience.

What question types are on the CAPM?

PMI's outline lists multiple-choice, drag-and-drop (enhanced matching), and animations and comic strips, and says you may also see hot spot questions. Online-proctored candidates see comic strips only, not animations. Our course uses multiple-choice and multiple-response questions.

Can I take the CAPM in Spanish?

Yes. PMI's certification handbook lists the CAPM in English, Arabic, Brazilian Portuguese, French, German, Italian, Japanese, Korean, Simplified Chinese, Spanish and Traditional Chinese. Our course is in English.

How many times can I take the CAPM?

Up to three times within your one-year eligibility period. After three attempts you wait one year from your last exam before you reapply.

Are these real CAPM exam questions?

No. All 900 course questions are original, written from PMI's public CAPM Examination Content Outline. Real exam content is confidential.

Keep going: CAPM exam format 2026 · CAPM vs PMP · el examen en español · PMP practice questions · PMP Study Guide book · all courses

SERÁ Academy is not affiliated with, endorsed by, or sponsored by PMI. PMI, CAPM, PMP and PMBOK are marks of Project Management Institute, Inc.